Carrington Apartments

Multi-Family Residential Development with Underground Parkade

Carrington Apartments

Project Type

Multi-Family Residential Development with Underground Parkade

Location

Carrington neighborhood, Northwest Calgary, Alberta

Timeline

Framing began on May 10, 2023 and was completed by early January 2024

Scale
  • Martennial Contracting Ltd. framed three six-storey buildings (Buildings 1, 3 & 4), each with 108 residential units, for a total of 324 units.
  • Total combined gross floor area: 304,162 square feet.
  • Each unit includes a private patio or deck, and each building integrates fire-rated and acoustically separated suites to meet strict multi-family building standards.

Project Details

The Carrington Apartments project was designed not just as a place to live, but as a space to build community and enhance day-to-day living for residents. Integrated directly into the residential buildings, a range of thoughtfully designed amenity spaces were included to support both convenience and lifestyle.

These amenities featured a games room, co-working and conference spaces, private meeting rooms, and a dedicated mailroom, offering residents access to shared spaces for work, socializing, and everyday needs. Practical additions like bike parking, storage lockers, and a dog/bike wash station were also included, reflecting a focus on functionality and resident comfort.

Together, these features positioned Carrington Apartments as a well rounded, modern living environment suited for individuals and families who value both private space and accessible, on-site services.

Location:

Carrington neighborhood, Northwest Calgary, Alberta

Date:

January 2024

Our Role:

Our Approach

The project included a total of 324 residential units across three six-storey buildings. Each unit was designed with a private patio or deck, enhancing outdoor living space and contributing to the overall architectural appeal.

Martennial Contracting Ltd. completed the full wood-frame construction of Buildings 1, 3, and 4. This included engineered floor systems, roof trusses, and a wide range of fire- and acoustically-rated wall assemblies.

Key materials used throughout the build included:
• 2×4 and 2×6 SPF lumber for structural framing
• 5/8” Type ‘X’ gypsum board for fire-rated assemblies
• R20 batt insulation with 6-mil poly vapor barrier
• Resilient channel systems and acoustic batt insulation
• Fiber cement siding, aluminum cladding, and brick veneer for exterior finishes

Unique architectural features included private balconies or patios for every unit, high STC-rated walls between suites, and a clean, modern exterior finish that blended materials for both function and aesthetics.

Challenges and Solutions

During the Carrington Apartments project, the team encountered a few logistical challenges that required flexibility and site wide coordination. One notable disruption came when the primary lifting equipment was temporarily unavailable. This impacted material handling and slowed production during a critical framing stage. To adapt, We supplemented with alternate lifting equipment, including a Roto and mobile crane, and adjusted site logistics to keep progress moving safely and efficiently.

In addition, there were periods where site sequencing and scheduling limitations required framing on one of the buildings to be delayed, allowing other trades time to catch up. While this change in workflow reduced some of the momentum built from simultaneous framing, the team worked within the updated schedule and realigned resources accordingly.

Delays in the delivery of prefabricated components also added some complexity to the overall timeline. By modifying installation plans and adapting movement strategies on short notice, Martennial was able to maintain consistent progress across all three buildings.

These types of challenges are common on projects of this scale, and navigating them successfully relied on clear communication, adaptability, and a collaborative approach with all site teams.

Team and Process

Martennial Contracting was responsible for the complete framing scope on Buildings 1, 3, and 4, which included structural floor systems, wall framing, roof assemblies, and integrated features such as fire- and acoustically-rated walls. The team’s work played a critical role in maintaining the construction timeline and supporting the structural integrity of the entire development.

Approximately 20 to 30 crew members contributed to the project at various stages, with teams rotating across buildings to maintain momentum. Martennial’s team brought together a diverse group of skilled workers with varying backgrounds and experience levels, which helped foster a collaborative and adaptable work environment.

A standout aspect of the project was the ability to maintain consistent quality across three large buildings, despite changing site conditions, equipment limitations, and shifts in schedule. Building floor systems, decks, and roof structures at ground level to enhance safety and productivity also stood out as an efficient and practical approach that benefited the entire site.

Client Vision & Collaboration 

The client’s vision for the Carrington Apartments project was to create a modern, high-density residential development that combined durability, efficiency, and comfort. The design emphasized long-term value, with features such as private outdoor spaces for every unit and high-performing fire- and sound-rated wall systems to enhance resident experience.

Martennial aligned with this vision by delivering precise, high-quality framing that supported the architectural intent and met all structural and code requirements. The team ensured each phase of framing—from floor systems to roof structures—was completed efficiently, contributing to the overall flow of construction and helping keep the project on track.

Communication throughout the build was handled collaboratively between site teams, consultants, and project management. Regular coordination and consistent updates ensured that adjustments could be made as needed, keeping everyone aligned and focused on delivering a strong final product.

Results and Impact

During the Carrington Apartments project, the team encountered a few logistical challenges that required flexibility and site wide coordination. One notable disruption came when the primary lifting equipment was temporarily unavailable. This impacted material handling and slowed production during a critical framing stage. To adapt, We supplemented with alternate lifting equipment, including a Roto and mobile crane, and adjusted site logistics to keep progress moving safely and efficiently.

In addition, there were periods where site sequencing and scheduling limitations required framing on one of the buildings to be delayed, allowing other trades time to catch up. While this change in workflow reduced some of the momentum built from simultaneous framing, the team worked within the updated schedule and realigned resources accordingly.

Delays in the delivery of prefabricated components also added some complexity to the overall timeline. By modifying installation plans and adapting movement strategies on short notice, Martennial was able to maintain consistent progress across all three buildings.

These types of challenges are common on projects of this scale, and navigating them successfully relied on clear communication, adaptability, and a collaborative approach with all site teams.

Client Feedback

Feedback from site staff and project partners highlighted Martennial Contracting’s responsiveness, accountability, and adaptability throughout the Carrington Apartments project. The team was recognized for maintaining consistent framing quality, clear communication, and the ability to adjust quickly to changing site conditions.

0 Units

Built in 3 buildings

0 - Six Storey Buildings

Built to Completion

0 sq. ft

Total gross floor area

Top Reasons to Work with Martennial

We handle every detail, from planning to execution, ensuring a seamless construction process. Our project management services take the stress out of building, so you can focus on the big picture.

On-Time Delivery

Martennial ensures your project stays on schedule with prompt and reliable service.

Skilled Craftsmanship

Our team brings expertise and precision to every framing project.

Safety Standards

A strong commitment to safety ensures a secure work environment for all involved.

Licensed and Insured

Rest easy knowing your project is handled by fully licensed and insured contractors.

Comprehensive Planning

Our thorough planning minimizes risks and optimizes efficiency in your project.

Reliable Communication

Stay informed every step of the way with clear and consistent updates.

Experienced Team

Years of industry experience make us trusted professionals in framing construction.

High-Quality Materials

We use premium materials to guarantee long-lasting structural integrity.

Positive Reputation

A proven track record of successful projects makes us a top choice for framing needs.

Martennial Contracting excels in framing buildings—precision work delivered on schedule and within budget. Dependable, skilled, and efficient, they set the standard for quality craftsmanship. Highly recommend for any project!

Logan Hartwell

Calgary, AB.